Primavera p6 rate types and how to use them, introduction to primavera p6 rate types.

Primavera P6 allows the user flexibility when it comes to rate types and types of project costs. Project teams may run into situations where different rate types are necessary depending on the type of project that is being set up. For example, one project schedule may require internal costs only, while a proposal project schedule may require an external rate that includes fees and other associated costs in the project.

Primavera P6 allows the project team to assign up to five different rate types to assignments in the project schedule. In addition, any of these five rate types can be set up as the default rate in Primavera P6 and for new resources. This article will address how to set up different rate types in Primavera P6.

Setting Up the Rate Type

The first part of the process can be performed with the Primavera P6 project open or closed. The Primavera P6 user must first establish a user-defined title for the rates. Go to the Admin tab and select “Admin Preferences…”:

assignment rate type in primavera

When the Admin Preferences dialog box opens, select the Rate Types tab on the left side of the screen and highlight one of the rates that you want to change:

assignment rate type in primavera

Once highlighted, you can change the user-defined title of the rate type. In this example we are going to use an external proposal rate:

assignment rate type in primavera

Go to the Enterprise tab and select “Resources”. In this example we will assign the new external rate to the Operator under our Trades category in Primavera P6:

assignment rate type in primavera

Right-click and select “Columns” and then “Customize…”:

assignment rate type in primavera

The Columns dialog box will open and you will be able to see the new rate type under the General section. Select the new rate type and use the top arrow in the middle of the dialog box to move the selection over to the Selected Options area and then click “OK”:

assignment rate type in primavera

Go back to your resources tab and you can see that the new rate type has been added to the assigned resource. Take note that the “Calculate Costs from units” checkbox is checked by default. This option means that new assignments for this role will automatically have their costs recalculated when there is a quantity update. Primavera P6 will also default to hours for the unit value. A project team member can input a price and the unit will default to hours.

assignment rate type in primavera

Go to the Primavera P6 bottom section and select the Units & Prices tab. Right-click on the header and select “Customize Resource Rate Columns…”:

assignment rate type in primavera

The Resource Rate Columns dialog box will open. Select the new rate type from the Available Options and use the arrow in the center of the dialog box to transfer the selection to the Selected Options section and click “OK”:

assignment rate type in primavera

You can see the new rate type:

assignment rate type in primavera

Assigning a Rate Type as a New Default Setting

To assign the new rate type as the default rate type for a new resource assignment in Primavera P6, select the Projects tab and select and highlight your current project. Go to the Resources tab at the bottom of the Primavera P6 screen and use the pull-down menu to select the new rate type under “Specify the default Rate Type for the new assignments”:

assignment rate type in primavera

Primavera P6 will now assign the new rate type to new resources assigned to this project by default.

New Resource Assignments and the New Rate Type

To assign a new resource that will employ the new rate type, the project must be open first. In this example, we will highlight the task “Explore Opportunity” and select the Resources tab from Primavera P6’s bottom menu.

Select “Add Resource” and choose Operator under the Trades category. Click the green plus sign to add this new resource to the highlighted task:

assignment rate type in primavera

Take note of the pay rate default that we set for this resource from our previous steps:

assignment rate type in primavera

Primavera P6 gives the project team flexibility when assigning rate types to resources and roles. Planning boasts more accuracy when different rates are employed since not all project costs are the same and different rates are often required for internal versus external costs. Using up to five saved and pre-determined rate types means that the project team can keep internal costs separate from external costs that may include a fee.

Contact Leopard Project Controls for your construction scheduling project .

Share This Blog, Choose Your Platform!

Our services.

  • BASELINE P6 SCHEDULE
  • PROGRESS UPDATE & REPORTING
  • CONSTRUCTION DELAY ANALYSIS
  • 4D SCHEDULING
  • FREE BID SCHEDULE DEVELOPMENT

CONTACT INFO

Florida Office

  • 2820 US Highway 1 S, Suite H, Saint Augustine, Florida 32086

New York Office

  • (In LOVE Building) 1350 Ave of the Americas, Fl 2 -1063 New York NY 10019

Virginia Office

  • 1550 Wilson Blvd, Suite 700, Arlington, VA 22209
  • [email protected]
  • (833) 777-6276
  • (833) 77-P6CPM
  • consultleopard.com

Seyar Azadani, Construction Scheduling Consultant

SEYAR AZADANI, PMP

President & ceo.

Seyar Azadani has over 20 years of CPM scheduling and construction management experience working with general contractors and project owners, including the USACE, DOT, VA, Meta, QTS, Turner, Donohoe Construction, and Whiting-Turner company. As a Construction CPM Scheduling Consultant, Seyar has provided Primavera P6 CPM Scheduling services for government agencies and the private sector, representing owners, general contractors, construction managers, and architects.

Seyar has proven knowledge, expertise, and experience in utilizing Oracle Primavera P6, Primavera P6 Team Member, Primavera Unifier, Bluebeam, MS Project, Procore, eBuilder, Tableau, Navisworks, and Autodesk Revit. As a project controls specialist, Seyar has assisted Meta and QTS with Data Center projects, including new build projects, retrofit projects, and leased spaces.

Seyar has provided project controls services to projects ranging from civil to industrial to high-rise construction, including hospitals and healthcare facilities, roads and highways, high-rise apartment buildings, and commercial projects, utilizing Primavera and MS Project CPM scheduling tools to create and maintain the CPM schedules for his clients. With the US Army Corps of Engineers projects, as a contractor and construction manager, Seyar has built military facilities, including completing the construction of a USACE training facility, a $200+ million project in the capacity of project construction director.

Seyar has a Master of Science degree in Construction Management from New York University (NYU) in Jan of 2012 and a Bachelor of Science degree in Civil Engineering in 2004.

Seyar Azadani

assignment rate type in primavera

Great Services

We are fully committed to delivering outstanding project controls solutions to our clients.

assignment rate type in primavera

TRUSTED CONSULTANTS

We are trusted by some of the best-known AEC firms in North America.

FAST TURNAROUND AND COST-EFFECTIVE PROJECT CONTROLS SERVICES

At Leopard, our certified and experienced project controls specialists are committed to delivering excellent project controls services to our clients in a timely and cost-effective manner.

  • Certified Small & Micro Business in the SWaM Program of Virginia’s DSBSD

Florida DOT Certified DBE Business, and Florida Certified Minority-owned Business Enterprise

  • Certified SWaM Business with The U.S. SBA

assignment rate type in primavera

A certified DBE and Minority-owned (MBE) Business Enterprise, Leopard Project Controls provides CPM Scheduling Services, Owner’s Rep Services, and Construction Management Support Services.

Licensed and Insured Florida Certified General Contractor License Number: CGC1534435

OUR OFFICES

  • 1350 Ave of the Americas, Fl 2 -1063 New York NY 10019

assignment rate type in primavera

  • CPM Scheduling
  • 4D Scheduling
  • Owner's Representative
  • Baseline P6 Schedule
  • Project Schedule Review Support
  • Progress Update & Reporting
  • Construction Delay Analysis
  • Free Bid Schedule Development

Copyright 2023, Leopard Project Controls, LLC. All Rights Reserved. Oracle® and P6® are registered trademarks and brands of Oracle Corporation and/or its affiliates. All other marks are the property of their respective owners.

  • Privacy Policy |
  • Terms of Use |
  • Refund Policy |
  • Contact Us |
  • P6 Training |
  • Setting the Baseline in MS Project and Change Management Baseline Updates
  • Creating Special Calendars in MS Project to Run Your Project More Efficiently and Identify Risks
  • Setting the Baseline in Primavera and Change Management
  • Interpreting the Primavera P6 Schedule Log
  • Assigning Roles and Resources in Primavera P6
  • The Best of Primavera P6 Activity Layouts
  • Importing and Exporting with Excel and Primavera P6
  • Using Advanced Filters in Primavera P6
  • Using Custom User-Defined Fields in Primavera P6
  • Importing & Exporting XER & XML Files in Primavera P6
  • Primavera P6 Global Changes
  • Export of a Primavera P6 Schedule without Costs
  • Creating Internal & External Relationships in Primavera P6
  • Creating WBS & Activity Codes in a Schedule Organization in Primavera P6
  • Financial Periods & Storing Period Performance in Primavera P6
  • Creating and Using Reflections in Primavera P6
  • Managing Project Health with the To Complete Performance Index (TCPI)
  • Using and Managing Primavera P6 Issues
  • Using and Managing Primavera P6 Notebook Topics
  • Using and Managing Primavera P6 Thresholds
  • Removing Partial and All Logic within the Primavera P6 Schedule
  • How to Create a Driving Predecessors Report in Primavera P6
  • Suspending Project Work in Primavera P6
  • Primavera P6 Visual Appeal and Formatting
  • Using Primavera P6 Steps
  • Primavera P6 Top-Down Estimation Process
  • Primavera P6 Rate Types and How to Use Them
  • Everything You Want to Know About the New Primavera P6 Version 20.12
  • Focus on Schedule Lag in Primavera P6
  • Concepts of Building Information Modeling (BIM) and Primavera P6
  • 5D Building Information Modeling (BIM) and Cost Analysis
  • Scan to BIM and Its Role in the Construction Industry
  • Artificial Intelligence and Machine Learning
  • Other Publications
  • Terms & Conditions & Privacy Policy

​​ Primavera P6 Rate Types and How to Use Them By:  Melanie Calverley Introduction to Primavera P6 Rate Types Primavera P6 allows the user flexibility when it comes to rate types and types of project costs. Project teams may run into situations where different rate types are necessary depending on the type of project that is being set up. For example, one project schedule may require internal costs only, while a proposal project schedule may require an external rate that includes fees and other associated costs in the project. Primavera P6 allows the project team to assign up to five different rate types to assignments in the project schedule. In addition, any of these five rate types can be set up as the default rate in Primavera P6 and for new resources. This article will address how to set up different rate types in Primavera P6. Setting Up the Rate Type  The first part of the process can be performed with the Primavera P6 project open or closed. The Primavera P6 user must first establish a user-defined title to the rates. Go to the Admin tab and select “Admin Preferences…”:    When the Admin Preferences dialog box opens, select the Rate Types tab on the left side of the screen and highlight one of the rates that you want to change:    Once highlighted, you can change the user-defined title of the rate type. In this example we are going to use an external proposal rate:     Go to the Enterprise tab and select “Resources”. In this example we will assign the new external rate to the Operator under our Trades category in Primavera P6:     Right-click and select “Columns” and then “Customize…”:    The Columns dialog box will open and you will be able to see the new rate type under the General section. Select the new rate type and use the top arrow in the middle of the dialog box to move the selection over to the Selected Options area and then click “OK”:    

Go back to your resources tab and you can see that the new rate type has been added to the assigned resource. Take note that the “Calculate Costs from units” checkbox is checked by default. This option means that new assignments for this role will automatically have their costs recalculated when there is a quantity update. Primavera P6 will also default to hours for the unit value. A project team member can input a price and the unit will default to hours.   Go to the Primavera P6 bottom section and select the Units & Prices tab. Right-click on the header and select “Customize Resource Rate Columns…”:    The Resource Rate Columns dialog box will open. Select the new rate type from the Available Options and use the arrow in the center of the dialog box to transfer the selection to the Selected Options section and click “OK”:    You can see the new rate type:     Assigning a Rate Type as a New Default Setting To assign the new rate type as the default rate type for a new resource assignment in Primavera P6, select the Projects tab and select and highlight your current project. Go to the Resources tab at the bottom of the Primavera P6 screen and use the pull-down menu to select the new rate type under “Specify the default Rate Type for the new assignments”:  Primavera P6 will now assign the new rate type to new resources assigned to this project by default. New Resource Assignments and the New Rate Type To assign a new resource that will employ the new rate type, the project must be open first. In this example, we will highlight the task “Explore Opportunity” and select the Resources tab from Primavera P6’s bottom menu.  Select “Add Resource” and choose Operator under the Trades category. Click the green plus sign to add this new resource to the highlighted task:   

Take note of the payrate default that we set for this resource from our previous steps:   Conclusion Primavera P6 gives the project team flexibility when assigning rate types to resources and roles. Planning boasts more accuracy when different rates are employed since not all project costs are the same and different rates are often required for internal versus external costs. Using up to five saved and pre-determined rate types mean that the project team can keep internal costs separate from external costs that may include a fee.

​© 5/25/2021

Original article by author, Melanie Calverley, first posted by Leopard Project Controls at:  https://consultleopard.com/primavera-p6-rate-types-and-how-to-use-them/

Copyright © 2017 - 2023 Melanie Calverley, Calverley Consulting, LLC. All Rights Reserved.

This website uses cookies to enhance your browsing experience.

Projects Analytics

Call us for more information:

1-800-931-1582, primavera tutorial : resource assignments window.

by Mary W | Aug 22, 2017 | Primavera Tutorial | 0 comments

Primavera P6 Training

primavera-p6-training computer

Welcome back to our  training  blog! Today we are going to cover the resource assignments window in Primavera P6.

The Resource Assignments window allows you to view and add resource & role assignments to activities in your current projects. Information regarding resource cost and quantity can also be viewed in spreadsheet format.

Here are some quick things to remember about the Resource Assignments window:

  • The Resource Assignment pane shows a list of the currently opened project’s (or projects) resource assignments and details. The layouts in this pane can be grouped by resource, role, activity, project, cost account as well as many other options. Additionally, users can apply filters and modify the columns.
  • The Resource Usage spreadsheet illustrates resource usage and cost over time.
  • The Display options bar selects the timescale interval and can change the values in the Resource Usage spreadsheet.
  • The Assignment Details window contains the General and Planning tabs
  • Use the General tab to view and modify assignments
  • Use the Planning tab to enter units, units/time, and duration

The General tab

The General tab is where you can find all of the information about the assignment, such as the resource and role assignment. This is where you can specify a resource’s rate type. The rate type determines the price per unit used to calculate the cost for the assignment.  A resource can also be assigned as the primary resource in the General tab.

You can also use the General tab to adjust the resource assignment. For example, if a resource is over-allocated, the general tab can be used to replace the resource with an alternative resource.

The Planning tab

The Planning tab is where all the resource information is stored.  When a user assigns a resource to activity, each field shows the specific resource information based on: 

  • The activity duration
  • The calendar assigned to the resource
  • Its default units per time

The Planning tab can also be used to adjust a resource’s units, etc for an activity to help manage allocations.

The Resource Assignments Window video below also demonstrates how to view and modify non-linear resource assignments by assigning a resource curve to an activity assignment by adding the resource curve column to the Resource Assignments pane.

  • Asta Software Training Videos
  • Free Primavera P6 Training
  • Primavera P6
  • Primavera P6 Training Online
  • Primavera Project Management
  • Primavera Training
  • Primavera Tutorial
  • Professional Project Management
  • Project Management Software
  • Project Portfolio Management
  • Risk Management
  • Uncategorized
  • February 2021
  • December 2020
  • August 2017
  • October 2016
  • September 2015
  • August 2015
  • February 2014
  • December 2013
  • November 2013
  • October 2013

Calculating cost when using multiple resource rates

The total cost for a resource assignment takes into consideration any changes in the price/unit over the course of the activity.

When connected to a P6 Professional database: Enter a price/unit for each rate type (defined in Admin Preferences, Rate Types) in the Units & Prices tab in the Resources window.

When connected to a P6 EPPM database: An application level setting determines whether cost spreads account for changes in resource and role rates over time. Enter a price/unit for each rate type (defined in P6, Application Settings) in the Units & Prices tab in the Resources window.

Select the rate type you want this assignment to use in the Resources tab in the Activities window. The cost of the resource assignment is based on the Rate Type assigned to the resource assignment.

For example, a 3-day activity has a resource that works 8 hours per day. The activity begins on Monday, 12-Aug-02 8:00 AM and ends on Wednesday, 14-Aug-02 5:00 PM. Price/unit for the resource is defined as:

The cost of the first 16 hours of the resource assignment is $160 (16 hours x $10.00/ hr). The cost for the last 8 hours of the resource assignment is $240 (8 hours x $30.00/ hr). The total cost for the resource is $400.00 ($160.00 + $240.00).

  • If you have resources with shifts that use timesheets, costs calculate using the price of the first shift for the resource.
  • When activity dates change, run Recalculate Assignment Costs to update resource costs based on the new dates.
  • Multiple resource rates are not reflected in the Activity Usage Spreadsheet or Resource Usage Spreadsheet.

Legal Notices | Your Privacy Rights Copyright © 1999, 2021

Last Published 12/7/2021

Last Published Tuesday, December 7, 2021

Project Assignment List

Review Resource Assignments in a Project or Program

The Assignment List page at the project level displays all of the resources assigned to the project. This page is also available at the program level for resources assigned to the projects within the program.

You can view resource assignments and their data in two different layouts: Grid or Spreadsheet.

Use the standard Grid layout for a view of total values for your resource assignments and their data. The data is displayed in customizable columns and grouping criteria depending on your needs. Because the Grid layout doesn't include a breakdown of the data over time, you can use this view to report high-level data to stakeholders. Some cells can be updated by selecting the cell and entering a new value or selecting a value from the drop-down options available. Multiple cells can be updated with the same value by selecting the highlighted corner of the cell and clicking-and-dragging the cell up or down to fill-up or fill-down the rows in that column with the selected cell value. You can also use Shift + Click to highlight multiple cells or use Ctrl + Click to select multiple cells, and then use the right-click Fill Down menu option.

Spreadsheet

Use the Spreadsheet layout to view resource assignments and their data in a customizable table format with a breakdown of values along the timescale configured for the page. Add vertical columns to view general information, dates and durations, and rolled up unit and cost fields for each resource. The same unit and cost fields can be displayed in horizontal spreadsheet rows so that their values can be analyzed along a timescale. Time-phased values for each row roll up to a corresponding Total column.

The first column of the table shows each resource assignment's name. Resources can be grouped by their activity assignments, associated roles, projects, codes, and more. These same fields can also be shown as columns. If a resource is grouped by a role or has an associated role listed in a column, it means that the role is staffed by the resource. If a resource is grouped by a role with a grouping band value of None, or if the associated role column is blank, it means that the resource is directly assigned to the project and has no associated role. If a resource name field is blank, it means that an unstaffed role is assigned to the project. You may need to add a column for role name or ID or group by roles to see which roles are staffed or unstaffed.

Some cells can be updated by selecting the cell and entering a new value or selecting a value from the drop-down options available. Multiple cells can be updated with the same value by selecting the highlighted corner of the cell and clicking-and-dragging the cell up or down to fill-up or fill-down the rows in that column with the selected cell value. You can also use Shift + Click to highlight multiple cells or use Ctrl + Click to select multiple cells, and then use the right-click Fill Down menu option.

If you're using the Spreadsheet layout to review an assignment list for a specific project, you can export and download a copy of the entire spread of resource and role data. Select Download Entire Spread in the lower toolbar to download. You will receive a notification when the file is ready to be downloaded.

You can save your page layouts as named views. Create as many named views as necessary for different displays of your data.

To review resource assignments in a project or program:

  • In the object selector, select a project or program.
  • In the sidebar, hover over  Resources or  Schedule , and select Assignment List .
  • On the Layout  menu, select Grid or Spreadsheet .
  • Select  Settings in the toolbar to configure view options such as columns, filters, grouping, timescale, spreadsheet rows, and currency.
  • Use columns to view resource details and rolled up values.
  • (Spreadsheet layout only) Use spreadsheet rows to view time-phased unit and cost values. To start the spreadsheet timescale at a specific date, in the Go to field, select a date.
  • Use the Search field to search for keywords in the table.
  • Update the value in a cell by selecting the cell and entering a new value or selecting a value from the options available. Not all cells can be edited from the assignments page.
  • Select the cell and then click-and-drag the corner of the cell box up or down to fill-up or fill-down those rows with the selected value.
  • Select a cell and then Shift + Click a cell in the same column to highlight multiple cells. Right click a highlighted cell and select Fill Down . The cells are updated with the value from the first cell you selected.
  • Select a cell and then Ctrl + Click multiple cells in the same column. Right click a highlighted cell and select Fill Down . The cells are updated with the value from the first cell you selected.
  • When you apply a filter to a view, the filter icon changes to indicate that the data on the page has a filter applied.
  • You can adjust column settings directly from the table using the  Open Column Menu of any column header. See Configure the Table from the List Page .
  • You can quickly delete activity resource assignments directly from this page. Select one or more resource rows, select the  Context menu, and then select Delete . To delete large groups of related assignments, group by Resource ID, Role ID, or Activity ID, select the  Context menu in a grouping band, and then select Delete .
  • If all labor or nonlabor assignments have been deleted from an activity, you will be prompted to retain or delete all unit and cost values of that assignment type. Select Yes to reset all activity labor or nonlabor unit and cost values to 0. Select No to retain the activity labor or nonlabor unit and cost values. After all material resources have been removed, all activity material costs will be reset to 0.
  • When an activity is set to Completed , you cannot use fill-down or fill-up with some date values from an In Progress or Not Started activity. If you do attempt to use fill-down or fill-up with data from a Not Started or In Progress activity, a warning icon is displayed, and the cell value is not changed. To remove the warning icon select the cell.
  • Activity data can sometimes be lost when cutting or copying and pasting assignments between more than one project in a program; however, existing timesheet records will always be associated with the pasted activity. This means that the user can see spread data for approved timesheet records. Any new timesheet data associated with approved records that is pasted into a new project will display in the destination project.
  • When performing fill-down or fill-up in the Rate Source column, the resource or role rate must match what is assigned to the activity.
  • To quickly view the details of the activity associated with the resource, select  Activity Details . The Activity Details panel displays important information such as Project name, WBS name, Start date with indicators for Actual Start date, Finish date with indicators for Actual Finish date, Status , Constraint indicators, and Percent Complete . See Configure Activity Date Indicators to enable indicators.
  • You can provide a hyperlink that directs team members to an internal or external site with more information than the grid can provide. See Create a Hyperlink in a Grid .

Next: Assignment List Fields

Last Published 3/20/2024

Last Published Wednesday, March 20, 2024

IMAGES

  1. Specify default rate type for new assignment Resources Settings in Primavera P6

    assignment rate type in primavera

  2. How To Create a New Project In Primavera P6 Using Project Wizard?

    assignment rate type in primavera

  3. How to add Assign and change Resource Rate Type in Primavera P6

    assignment rate type in primavera

  4. Pay Rates in Primavera P6 Professional

    assignment rate type in primavera

  5. Primavera P6 Rate Types and How to Use Them?

    assignment rate type in primavera

  6. How to do Rate types setting admin preferences of primavera p6

    assignment rate type in primavera

VIDEO

  1. A Simple P6 Layout for doing Earned Value

  2. User rate type of planning with non annualized budget total

  3. Masterclass: Travel Pay Myth Busters

  4. 🔴 How to find Resource Assignment discrepancies!

  5. Resource Creation and Assignment to Tasks

  6. Resource Assignment Spreadsheet Primavera P6

COMMENTS

  1. Primavera P6 Rate Types and How to Use Them

    To assign the new rate type as the default rate type for a new resource assignment in Primavera P6, select the Projects tab and select and highlight your current project. Go to the Resources tab at the bottom of the Primavera P6 screen and use the pull-down menu to select the new rate type under "Specify the default Rate Type for the new ...

  2. Assign a rate type to a resource assignment

    The rate type determines the price/unit used to calculate costs for the assignment. The names for each rate type are defined by your system administrator in the Rate Types tab of Admin Preferences when P6 Professional is connected to a P6 Professional database and in P6 when connected to a P6 EPPM database. When you select a rate type, the ...

  3. Primavera P6 Rate Types and How to Use Them

    To assign the new rate type as the default rate type for a new resource assignment in Primavera P6, select the Projects tab and select and highlight your current project. Go to the Resources tab at the bottom of the Primavera P6 screen and use the pull-down menu to select the new rate type under "Specify the default Rate Type for the new ...

  4. Specifying Resource Assignment Rates

    To specify resource assignment rates: Click Projects. On the Projects navigation bar, click Activities. On the Activities page, select an activity in the table and click the Assignments detail window. In the Assignments detail window: Add the Rate Type and Rate Source columns. Select an option for the type and source. Save your changes.

  5. Configure Assignment Calculation Options

    Rate Type: Identifies which rate source rate, for the rate source's current availability period, to use as the assignment's Price/Unit value. If the rate source is Resource or Role, you can choose one of the rate source's five rate types. If the rate source is Override, the rate type value will be set to Custom Rate and the Price/Unit value ...

  6. Pay Rates in Primavera P6 Professional

    You provide the rate type descriptor and the associated hourly pay rates for each resource. Set the assignment default rate type and Primavera P6 Professional will use this pay rate type for all new resource assignments. In this article we describe how to define an external pay rate, set the assignment default for this pay rate definition, and ...

  7. Choose the rate source for an assignment

    Choose Project, Activities. Select the activity that contains the assignment. Display Activity Details, then click the Resources tab. In the Resources tab, double-click the Rate Source column and choose Resource, Role, or Override. Choose Resource to calculate cost based on the resource's price/unit value selected in the Rate Type column.

  8. Usage of Rate Types In Primavera P6

    In this tutorial, let us learn the usage of Rate types in Primavera P6.As a scheduler, you might be requiring to maintain both internal and external reports....

  9. How to add Assign and change Resource Rate Type in Primavera P6

    🔴WHAT YOU'LL LEARN/SEARCH TITLES: Primavera P6: Adding, Assigning, and Changing Resource Rate Types Manage Resource Rates in P6: Adding, Assigning, and Chan...

  10. Resource-Loaded Scheduling Overview

    Configure Assignment Calculation Options: The cost of a resource or role assignment is determined by its units and its rate. Before you enter units and costs on an assignment, you should specify the source of the assignment's rate, the type of rate, and whether the assignment's costs should be calculated in proportion to its units or ...

  11. Understanding Role Availability and Rates

    When a role is staffed with a resource, the assignment can be adjusted to either use the role's pay rate or the resource's pay rate. Resource and role rates are used to calculate the cost of each activity to which they are assigned. Next: Assignment List Overview. Last Published Wednesday, March 20, 2024. Oracle Primavera Cloud Help.

  12. Specify default rate type for new assignment Resources Settings in

    #Softedemy,#PrimaveraP6,#SettingsIn this video, you will learn to Specify the default rate type for new assignment Resources Settings in Primavera P6 | Expla...

  13. Recalculating Resource Assignments and Duration Types in Primavera P6

    Because this option will recalculate the resource assignment data based on Duration type, you may want to modify the activity's current duration type. This can be done from the General tab of the Details section. There are four options available for Duration Type: Fixed Duration & Units, Fixed Duration and Units/Time, Fixed Units, and.

  14. Resources tab

    The rate type determines which price/unit is set on the assignment. For resources, the list corresponds to the rate types defined in the Rate Types tab in the Admin Preferences dialog box when P6 Professional is connected to a P6 Professional database and in the Application Settings in P6 when connected to a P6 EPPM database.

  15. PDF Creating a New Project in Primavera P6

    Now you will specify the default Assignment Rate Type. Every resource can have multiple hourly rates assigned to them for differnet types of work. For example, a labourer might be paid $30/hour for industrial work and $40/hour for commercial work. On this screen, you will pick the default rate type to use when you assign resources to activities.

  16. Assignment List Fields

    Rate Source. The value that indicates which Price/Unit will be used to calculate costs for the assignment. Valid options are Resource, Role, or Override. Rate Type. Identifies the Resource or Role rate to be used as a default when creating activity resource assignments. Resource Type. The resource type. Valid values are Labor, Nonlabor, and ...

  17. Primavera Tutorial : Resource Assignments Window

    The General tab is where you can find all of the information about the assignment, such as the resource and role assignment. This is where you can specify a resource's rate type. The rate type determines the price per unit used to calculate the cost for the assignment. A resource can also be assigned as the primary resource in the General tab.

  18. setting up the rate type in Primavera (P6)

    About Press Copyright Contact us Creators Advertise Developers Terms Privacy Policy & Safety How YouTube works Test new features NFL Sunday Ticket Press Copyright ...

  19. Using Pay Rates in Primavera P6 EPPM

    Set your desired pay rate type as the default for new activity assignments. Primavera P6 EPPM lists each of the five rate types in the Resources Administration Units & Prices bottom tab. Enter the default pay rate for each resource in your schedule. If you happen to change a resources rate type value you can use the recalculate assignment costs ...

  20. Calculating cost when using multiple resource rates

    Select the rate type you want this assignment to use in the Resources tab in the Activities window. The cost of the resource assignment is based on the Rate Type assigned to the resource assignment. For example, a 3-day activity has a resource that works 8 hours per day. The activity begins on Monday, 12-Aug-02 8:00 AM and ends on Wednesday, 14 ...

  21. ResourceAssignment

    The rate type that determines which of the five prices specified for the resource will be used to calculate the cost for the resource assignment. No. RemainingCost. The remaining cost for the resource assignment on the activity. Computed as remaining cost = remaining units * cost per time. No. RemainingCurve

  22. Entering Activity and Assignment Units and Costs

    All assignment cost values roll up to the corresponding activity fields. Depending on the activity's duration type, modifying an assignment's duration or units/time values may cause the assignment's units to change. If the assignment's Calculate Costs from Units setting is enabled, the change in its units will recalculate its costs. The updated ...

  23. Review Resource Assignments in a Project or Program

    Create as many named views as necessary for different displays of your data. To review resource assignments in a project or program: Navigate to the project or program resource assignments page. In the object selector, select a project or program. In the sidebar, hover over Resources or Schedule, and select Assignment List.